Issuing body
ASME
Latest edition
2023 Edition
Region
USA, Global
Equipment items
3
Scope
Power boilers, electric boilers, miniature boilers and HRSGs.
Key requirements (8)
- Power boiler construction (steam generator) — section governs design, materials, fabrication.
- Maximum allowable working pressure (MAWP) calculated per Section I formulas (PG-27 for tubes, PG-29 for shells).
- Joint efficiency E: 1.0 (full RT), 0.85 (spot), 0.70 (no RT) for longitudinal seams.
- Hydrostatic test: 1.5 × MAWP held minimum 30 minutes.
- Mandatory PWHT and impact testing thresholds — stricter than VIII.
- Watertube boiler MAWP often 100–200+ barg for utility; firetube to ~30 barg.
- Material: SA-516, SA-285, SA-106, SA-335 (P11/P22/P91), etc.
- Quality system / authorized inspection mandatory.